Siemens SGT400 gas turbine generator set
Scope of supply
1. The list below is Siemens SGT400 GTG set supply scope, which will be provided by seller
|
Siemens SGT400 GTG sets are currently installed |
||
|
Item |
Supply Scope |
Qty. |
|
1 |
- Main unit: Engine, gearbox, generator, including base and housing;
- Pry into the fuel system: shut-off valves, control valves, metering, etc;
- Lubrication and cooling system: oil pump, oil cooler, etc;
- AC/DC systems: chargers, AC/DC MCC, etc;
- Gas turbine intake system: air intake filter, intake silencer, etc;
- Hood ventilation system: ventilation filters, ventilation fans, silencers, etc;
- Unit CO2 fire extinguishing system: CO2 cylinders, detectors, alarms, control system, piping, etc;
- Unit start device: starter motor;
- Unit control system: unit control cabinet, control system hardware and software, etc. |
2 Set |
2. Siemens SGT400 GTG set basic information:
|
Engine |
Siemens SGT400 |
|
Fuel Nozzle |
NG |
|
Power: |
14.4MW |
|
Combustion Type |
DLE |
|
Manufacture time |
2018 |
|
Commissioning time |
2023 |
|
Rated Speed |
9525/1500 RPM |
|
Voltage |
10.5Kv |
|
Current status |
The two units were manufactured in 2018, put into operation after debugging in 2023, and ran for 243 and 237 hours respectively. |
|
Generator: |
ALLAN |
|
Frequency: |
50HZ |
3. Onsite pictures
Price
|
Item |
Description |
Item scope |
Unit Price (USD) |
Qty (e.a) |
Total-USD |
|
1 |
Siemens SGT400 GTG set |
2 |
12,000,000.00 |
2 |
24,000,000.00 |
|
TOTAL FOB SHANGHAI AMOUNT IN USD |
|
24,000,000.00 |
|||
Delivery time
Payment terms
-50% of contract amount shall be paid after the receipt of the products readiness from Seller.